Calculates a transformer's K-factor per ANSI/IEEE C57.110: the sum of squared harmonic currents weighted by the squared harmonic order, divided by the sum of squared currents. A purely sinusoidal load gives K equal to one; you pick the commercial class immediately above the computed value. Enter the fundamental and the odd harmonics up to the 13th.

Result

Why a transformer cooks with no overload on the meter

The transformer draws less than rated rms current, the breaker stays quiet, and the winding still runs past its thermal class. Harmonics are usually behind it: electronic loads pull distorted current, and eddy current loss in the conductors climbs with the square of frequency, so a 13th order component heats one hundred and sixty-nine times harder than a fundamental of matching amplitude. The K-factor turns a measured spectrum into a purchasing requirement, and anyone feeding a data centre, an inverter room, an LED bank or a drive lineup needs it before the order goes out.

Per ANSI/IEEE C57.110, K = Σ(Ih² × h²) ÷ Σ(Ih²), with h over the odd orders 1 through 13. Ih is the rms current at each order and h the order. Numerator and denominator carry the same dimension, so scale drops out: amperes, per unit values or percent of fundamental all work, as long as every entry shares one base. A purely sinusoidal load returns exactly 1. The spectrum on screen — 100, 33, 20, 14, 11, 9 and 7 A — returns 5.637, which pushes the specification to the next commercial class up, K-13. Common classes run K-4 for mixed load, K-13 for offices and schools thick with electronics, and K-20 for data centres; UL 1561 also lists K-9, K-30, K-40 and K-50.

The standard normalises harmonic currents against the rated current of the transformer, not against the measured sum. This page uses the sum you enter, so the value shown belongs to that waveform at full load: a unit running below nameplate suffers less than the number implies. The sum stops at the 13th order, so content between the 15th and the 25th comes out understated, where the squared weighting bites hardest. Mind the name too: the European factor K of HD 538.3.1 is a different quantity, a derating multiplier between 1 and 2. And 3rd and 9th order currents circulate inside a delta winding, so a primary reading on a delta-wye unit differs from a secondary one.

Frequently asked questions

Does a result of 5.637 call for a K-6 transformer?
There is no K-6. The classes are fixed catalogue steps, and the rule is to pick the one immediately above the computed value, so 5.637 points at K-13, while K-4 would sit under the requirement. Specifying low hands back the original problem, with the winding heating through eddy current loss while rms current still reads normal and insulation life shortening. Specifying far too high costs money as well, since a high class unit uses transposed conductor, a reinforced neutral and more material, and the price gap between K-13 and K-20 is not small.
Can I enter the harmonics as a percent of the fundamental?
Yes. The K-factor is a ratio between two sums of matching dimension, so multiplying every current by a constant leaves it untouched. Entering 100, 33, 20, 14, 11, 9 and 7 in amperes returns the same 5.637 as entering those figures as percent of fundamental, or as per unit values. Mixing bases is what breaks it: a fundamental in amperes beside harmonics in percent yields a meaningless number. Power quality analysers usually offer both views; pick one and hold to it all the way through.
When does the calculator refuse the values entered?
Only when the sum of the squared currents reaches zero, meaning all seven boxes hold zero. With no current there is no waveform to characterise and the denominator collapses. Every other combination is accepted, including leaving at zero the orders the analyser never measured, which is the correct thing to do: an absent harmonic adds zero to both sums and shifts nothing. Empty boxes get different treatment and raise no warning; the readout just holds a dash until all seven fields carry a value.

Related Tools

Buller-Woodrow Loss Factor

Estimates the loss factor of a distribution feeder from its load factor using the empirical Buller-Woodrow relation: loss factor = k × load factor + (1 − k) × load factor squared. The loss factor is the ratio of average loss to peak loss over the period, and it is what turns the instantaneous loss measured at peak hour into energy lost over the month without needing a recorded load curve. Because Joule loss varies with the square of the current, the loss factor always sits below the load factor, and the lower the load factor the lower the ratio between them: at a load factor of 0.20 the loss factor is under half of it, while at 0.80 it sits around 86% of its value. The coefficient k is an input rather than fixed at 0.30, the classic Buller-Woodrow value for distribution networks, because utilities recalibrate k between 0.15 and 0.50 according to the feeder load profile. Enter the load factor for the period and the coefficient k.

🔌

TDD — Total Demand Distortion (IEEE 519)

Converts total harmonic current distortion into total demand distortion, TDD = THD_I × I₁ ÷ I_L, where I₁ is the fundamental current at the moment of measurement and I_L the installation's maximum demand current. The difference matters a lot: THD has the instantaneous fundamental in its denominator, so a drive running at 20% load can read 60% THD while injecting negligible harmonic current into the grid. IEEE 519 sets its limits in TDD for exactly this reason, referencing everything to maximum demand — typically 5% TDD for installations with an I_sc/I_L ratio below 20, which is the criterion the utility enforces. Enter the measured current THD, the fundamental current at measurement and the maximum demand current.

📈

RLC Quality Factor Q Calculator

Computes the quality factor Q of a series RLC circuit from R, L and C using the ratio between reactance and resistance.

📈

Amplification Factor (Q)

Calculate the resonance amplification factor (quality factor Q), Q = 1 ÷ (2·ζ), from the damping ratio ζ. The dimensionless result shows how many times the vibration amplitude at resonance exceeds the equivalent static deflection: lightly damped systems (small ζ) have high Q and sharp, dangerous resonance peaks; well-damped systems have low Q and smooth response. It is central to designing structures, machines and instruments to avoid destructive amplification and to characterizing the selectivity of filters and resonators. Enter the damping ratio.

Three-Phase Voltage Unbalance (NEMA)

Measures the unbalance of the three line voltages of a three-phase system by the NEMA MG-1 criterion, the same one used by motor derating curves. The calculation takes the average of the three line voltages, finds the largest absolute deviation between any voltage and that average, and divides this deviation by the average, as a percentage. The number has a direct consequence: NEMA forbids operating induction motors above 5%, recommends derating from 1% on (at 2% the derating factor is already about 0.95) and warns that 1% of voltage unbalance can become 6 to 10% of current unbalance, with extra rotor heating. The NEMA definition was adopted (largest deviation divided by the average, also called LVUR) rather than the IEC and IEEE unbalance factor, which is the ratio between negative and positive sequence components and requires full phasors, not just magnitudes. Enter the three measured line voltages.

Arc Flash Incident Energy (Lee Method)

Computes arc flash incident energy by the Ralph Lee method, E = 5.12×10⁵ × V × I_bf × t ÷ d², with voltage in kV, bolted fault current in kA, fault clearing time in seconds and working distance in millimetres. Lee's method models an open-air arc as an ideal radiant heat source, ignoring the energy an enclosure reflects back; IEEE 1584 therefore keeps it only as the legacy model, recommended for open-air arcs and for voltages above 15 kV where the empirical equations do not apply. The result in cal/cm² sets the PPE category: 1.2 cal/cm² is the second-degree burn threshold and the value that bounds the arc flash boundary. The cal/cm² form is adopted (the J/cm² variant uses 2.142×10⁶ and is 4.184 times larger). Enter the voltage, the fault current, the clearing time and the working distance.